杰达拱形屋顶施工步骤
作者:杰达钢构 点击:1093次 时间:2021-11-22 12:04
![杰达拱形屋顶施工步骤拱形屋顶施工步骤 杰达拱形屋顶施工步骤拱形屋顶施工步骤](https://www.jiangsujieda.com/zb_users/upload/2021/10/2016031123290403403.jpg)
![杰达拱形屋顶施工步骤拱形屋顶施工流程 杰达拱形屋顶施工步骤拱形屋顶施工流程](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-15122623164X00.jpg)
![拱形屋顶施工流程2](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231GL38.jpg)
![拱形屋顶施工流程3](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231HL20.jpg)
![拱形屋顶施工流程4](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231J5363.jpg)
![拱形屋顶施工流程5](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231K63C.jpg)
![拱形屋顶施工流程6](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231P9254.jpg)
![拱形屋顶施工流程7](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231R5919.jpg)
![拱形屋顶施工流程8](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231S94I.jpg)
![拱形屋顶施工流程9](https://www.jiangsujieda.com/zb_users/upload/2021/10/2-151226231U1X8.jpg)
注:
1.江苏杰达钢结构工程有限公司根据建设单位或总包设计单位选定拱形彩板工程图的要求,无梁拱形屋顶部分由我公司设计和施工,将尽力做好与总承包设计、施工单位的协调工作。
2.土建工程施工到檐口上皮标高时,应按拱形屋顶构造要求准确留出所有埋件,下一工序转交杰达钢构施工人员进入工地进行拱形彩板安装,待做完通风、采光及喷涂室内保温层后即可退出现场。
3.施工现场要在建筑旁留有一定空地(其面积视工程大小而定)作为放自动滚压机车拖车制作拱板和堆放成型后的拱板用地,当屋面跨度较大时吊车设在室内吊装,因此施工要在山墙处留出入口。具体施工方案与土建施工单位协商确定。